Project Update

Construction of this project has been substantially completed. The contractor will return in the spring/summer of 2024 to complete remaining trail work on Fernbrook Lane and minor outstanding items. 


Cornerstone Rehab 2023Cornerstone 
Project Area Map (PDF)

Fernbrook Rehab 2024Fernbrook Lane Reclaim and 
Cimarron East and Minnesota Lane Mill and Overlay Project Area Map (PDF)

Project Overview

Improvements with this project include the rehabilitation of streets via a mill and overlay or reclamation. The Cornerstone area, Cimmaron East neighborhood, and Minnesota Avenue, as shown on the adjacent maps, are proposed to be milled and overlaid, which involves removing a portion of the existing pavement (milling) on the edges of the street and applying a new layer of asphalt over the entire roadway.

Fernbrook Lane between Hwy 55 and County Road 6, as shown on the project area map, is proposed to be reclaimed, which involves completely removing (reclaiming) the existing pavement and paving a new roadway surface.

Preventative maintenance will also be performed with the project which includes:

  • Installation of concrete pedestrian ramps, as necessary, in accordance with the Americans with Disabilities Act (ADA)
  • Replacement of concrete curb and gutter where the curb and gutter are in poor condition
  • Trail replacement
  • Repairs to water main valves
  • Repairs to storm sewer catch basins
  • Repairs to sanitary sewer manholes

Anticipated Schedule

  • Neighborhood Informational Meeting:
    Jan. 11, 2023, 5:30 p.m.
    City Hall, 3400 Plymouth Blvd
  • Public Hearing: 
    Apr. 25, 2023 at 7 p.m.
    City Hall, 3400 Plymouth Blvd
  • Construction:  summer - fall 2023