Project Update -November 13, 2024
Open House #2 for the 36th Avenue Rehabilitation Project is set for 4:30-6:30 p.m. Tuesday November 19, at Plymouth Community Center, 14800 34th Avenue. You are invited to meet the project team and view the final layout for the project. No formal presentation will be provided so please stop in at any time. Materials presented at the open house will also be available on the project webpage. Please reach out to the project team with any questions.
Project Overview
Project Area Map (PDF) |
36th Avenue between Kilmer Lane and Zachary Lane, as shown on the adjacent map, is scheduled for improvements in 2025 due to pavement age and underlying condition. It is anticipated that the project will involve completely removing (reclaiming) the existing pavement and paving a new roadway surface.
The need for pavement rehabilitation provides an opportunity to address additional traffic flow and pedestrian safety concerns in the area. The proposed improvements also include:
- Shifting the Kilmer Lane intersection west to align with Lancaster Lane with the addition of a traffic signal at the intersection.
- Shifting the 10’ Basset Creek Regional trail to the south side of the roadway from Hwy 169 to Zachary Lane / East Medicine Lake Boulevard. A local 8’ trail will remain on the north side.
- Modifying the roadway from Pilgrim Lane to Lancaster Lane to a three-lane section to create left turn lanes and adding medians to guide traffic to middle school accesses.
- Installation of flashing pedestrian beacons (RRFBs) and median refuges at Armstrong High School and Plymouth Middle School crossings.
Anticipated Schedule
- Studies and Data Collection: Complete
- Preliminary Design: Complete
- Open House #1: November 8, 2023
- Final Design: December 2023 - November 2024
- Open House #2: Tuesday November 19, 2024 from 4:30-6:30 p.m. at the Plymouth Community Center, 14800 34th Avenue
- Construction: Late April 2025 - November 2025
Additional Information
- Draft Plans - Draft construction plans for the project
- Open House Invitation - Postcard mailed for the Nov. 19, 2024 open house
- Draft Layout - Draft layout of the proposed improvements
- Project Notification Postcard - Postcard mailed to properties in the proposed project area
- Community Engagement Results - Community feedback and suggestions received in June 2023
- Open House Postcard - November 8th, 2023, Open House Invitation
- Open House Summary - Summary of feedback collected at the November 2023 Open House
- Interactive Comment Map - Map used to collect feedback on the existing conditions and proposed improvements
Contact
Joe Shamla, Assistant City Engineer
Plymouth City Hall | 3400 Plymouth Blvd. | Plymouth, MN 55447